SE The installation of the boards is done from bottom to top. Insert the board as shown in the picture! When using a hanging underlay, finish the spacers at the lowest point of the fabric.
NO The plates are mounted from bottom to top. Insert the plate as shown in the picture. If a hanging underlay is used, finish the spacers at the lowest point of the fabric.
EN The boards are mounted from the bottom up. Insert the board as shown! In the case of a hanging underlayment, finish the spacing at the lowest point of the underlayment.
SE Fastening (A): Corrosion-protected Rapid 140/10 (or equivalent) alternatively galvanized roofing nail 25 x 2.5 mm. Joint taping (B): Sealing Tape T-Flex. Fixation (C): For c1200 finish with a screwed wooden block. (NOTE! The screw must not go through the roof underlay!) Clamp the board against the block.
NO Fastening (A): Corrosion-protected Rapid 140/10 (or equivalent) or galvanized roofing nails at 25 x 2.5 mm. Joint tape (B): Sealing tape T-Flex. Fixation (C): For c1200, finish with a screwed wooden block. (NOTE! The screw must not go through the roof underlay!) Press the plate firmly against the block.
EN Mounting (A): Corrosion-resistant Rapid 140/10 (or equivalent) or 25 x 2.5 mm galvanised roofing nails. Splice taping (B): T-Flex sealing tape. Fixation (C): For c1200, finish with screwed wooden blocks. (Note: The screw must not penetrate the roof underlayment!) Tighten the board against the block.